| B8 & Ave 2 ½ E Drainage Improvements |
| |
Project No.: |
B-08-A-(200)A / H673501C |
| |
Location: |
Business 8 between Pacific Ave and Ave 3E |
| |
Contractor: |
Currently Advertised |
| |
Programmed Cost: |
Estimated at $400,000 |
| |
Scope: |
Project consists of drainage improvements, such as new pipes, catch basins, and retention basins, which will help with water ponding along Business 8. |
| |
Expected Project
Duration: |
Approximately 2 to 3 months |
| |
County 14th Street, Ave 3E to Ave 6 ½ E |
| |
Project No.: |
ARRA-YYU-0(200)A / SS86001C |
| |
Location: |
Along County 14th Street from Ave 3E to Ave 6 ½ E |
| |
Contractor: |
Cemex Construction Materials South, LLC. |
| |
Programmed Cost: |
$999,671.58 |
| |
Scope: |
Project consists of overlaying existing roadway |
| |
Expected Project
Duration: |
Approximately 4 months |
| |
I-8, Gila Bend – Milepost 121 |
| |
Project No.: |
STP-008-A-(203)A / H682901C |
| |
Location: |
Interstate 8 from MP 115- to MP 121 |
| |
Contractor: |
Project has bid opened and will now go to transportation board for review. |
| |
Programmed Cost: |
|
| |
Scope: |
Project consists of milling and replacing AC pavement and AR-ACFC. Construction of guardrail, guardrail reconstruction, and replacement of bridge dados, and other misc. items. |
| |
Expected Project
Duration: |
Estimated to be 7.5 months |
| |
I-8 Micro Seal Milepost 134.6-141 |
| |
Project No.: |
IM-008-B(202)A / H791701C |
| |
Location: |
Interstate 8 from MP 134.6-141 |
| |
Contractor: |
Southwest Slurry Seal, Inc. |
| |
Programmed Cost: |
$964,040.06 |
| |
Scope: |
Project consists of crack sealing existing pavement, micro sealing existing roadway, new pavement markings, etc. |
| |
Expected Project
Duration: |
|
| |
I-8, Milepost 15 Rock Fall Containment |
| |
Project No.: |
IM-008-A-(208)A / H545301C |
| |
Location: |
Interstate 8 from MP 15-21 |
| |
Contractor: |
R.E. Monks Construction |
| |
Programmed Cost: |
$2,085,893.76 |
| |
Scope: |
Work consists of removing rock slope and providing rock protection, including concrete barrier, limited scaling, pavement markings, drainage pipe, and other related items. |
| |
Expected Project
Duration: |
Estimated at 6 months |
| |
I-8, Milepost 121 to Big Horn (MP 134.6) |
| |
Project No.: |
ARRA-IM-008-B(200)A / H701601C |
| |
Location: |
Interstate 8 from MP 121 – 134.6 |
| |
Contractor: |
Project has bid opened and will now go to transportation board for review. |
| |
Programmed Cost: |
|
| |
Scope: |
Project consists of milling existing AC and replacing with new AC and AR-ACFC, other items include replacing pavement markings, seeding, etc. |
| |
Expected Project
Duration: |
Estimated at 7.5 months |
| |
I-10, Milepost 70.6 – 80 Micro Seal |
| |
Project No.: |
IM-010-A-(202)b / H792101C |
| |
Location: |
Interstate 10 from MP 70.6 – 80 |
| |
Contractor: |
Southwest Slurry Seal, Inc. |
| |
Programmed Cost: |
$1,233,304.40 |
| |
Scope: |
Project consists of crack sealing existing pavement, micro sealing existing roadway, new pavement markings, etc. |
| |
Expected Project
Duration: |
|
| |
I-10, West Quartzsite TI Spot Repair |
| |
Project No.: |
IM-010-A(203)A / H792901C |
| |
Location: |
In the Town of Quartzsite at exit 17 along Interstate 8 |
| |
Contractor: |
Scheduled for advertisement in calendar year 2010. |
| |
Programmed Cost: |
|
| |
Scope: |
Project consists of milling existing crossroad and traffic interchange on and off ramps and replacing with AC and ACFC. New pavement markings and other related items of work are included. |
| |
Expected Project
Duration: |
|
| |
SR 85, Town of Gila Bend (Gila Bend Airport) |
| |
Project No.: |
ARRA-GBD-0-(203)A / SS85801C |
| |
Location: |
On SR 85 at the Gila Bend Airport |
| |
Contractor: |
Project has bid opened and will now got o transportation board for review. |
| |
Programmed Cost: |
Estimated at $205,000 |
| |
Scope: |
Project work consists of constructing new paved parking lot, installation of PVC conduit for future service and retention basin grading. |
| |
Expected Project
Duration: |
|
| |
| SR 95, Holiday Harbour |
| |
Project No.: |
H638001C |
| |
Location: |
Along SR 95 from MP 156.8 – MP 157.6 |
| |
Contractor: |
Currently under design |
| |
Programmed Cost: |
|
| |
Scope: |
Widening existing roadway to include two-way left turn and construction of new concrete box culvert and drainage improvements |
| |
Expected Project
Duration: |
Project expected to advertise for construction in June 2010 |
| |
| SR 195 I-8 to US 95 - Design Concept Report |
| |
Project No.: |
195 YU 27 H7043 01L |
| |
Location: |
State Route (SR) 195 between Interstate 8 and US 95 in Yuma |
| |
Contractor: |
The Arizona Department of Transportation (ADOT) and the Federal Highway Administrations (FHWA) |
| |
Scope: |
Engineering and environmental studies have been initiated to determine what improvements would be needed. |
| |
Expected Project
Duration: |
Summer 2009: Finalize study and environmental documents; FHWA approval. |
| |
|
|
US 80 Bridge Replacement Red Top Wash |
| |
Project No.: |
BR-YYU-0-(031)A / SB41501C |
| |
Location: |
Along US Highway 80 |
| |
Contractor: |
Bison Contracting Co. |
| |
Programmed Cost: |
$1,529,874.25. |
| |
Scope: |
Project consists of demolishing existing bridge and building new bridge. |
| |
Expected Project
Duration: |
Approximately 8 to 9 months |
| |
US 95, 16th Street Widening |
| |
Project No.: |
ARRA-095-A(201)A / H705301C |
| |
Location: |
On US 95 from MP 23.95 - 24.66 |
| |
Contractor: |
Royden Construction Co. |
| |
Programmed Cost: |
$8,962,995.21 |
| |
Scope: |
Reconstruction and widening of existing five lane section to 6 lanes with concrete median separation. Widening two bridge structures.
For more information please view web site or call the project hotline at 1.877.397.5202. |
| |
Expected Project
Duration: |
|
| |
| US 95 Milepost 42 to Milepost 66 - Design Concept Report |
| |
Project No.: |
095 YU 42 H7022 01L |
| |
Location: |
US 95 between approximate MP 42 and MP 66, located on the U.S. Army Yuma Proving Ground (YPG) in Yuma and La Paz Counties, Arizona. |
| |
Contractor: |
The Arizona Department of Transportation (ADOT) and the Federal Highway Administrations (FHWA) |
| |
Scope: |
An engineering and environmental study is being completed to determine what improvements are needed for the future operation of US 95 between approximate MP 42 and MP 66. |
| |
Expected Project Duration: |
|
| |
|
|
US 95, Peligro to Clarks Milepost 51 – 80 |
| |
Project No.: |
ARRA-095-B(200)A / H584101C |
| |
Location: |
On US 95 MP 51 – 80 |
| |
Contractor: |
Fisher Sand & Gravel dba Southwest Asphalt Paving |
| |
Programmed Cost: |
$6,830,000 |
| |
Scope: |
Overlay roadway with 3” Asphaltic Concrete and lining existing pipes |
| |
Expected Project
Duration: |
Expected to be complete by May 2010 |
| |
Documents are posted as they become available in PDF format, which requires Adobe Reader to view. |