Safford Construction ORG 8430
I-10 Luzena Road – San Simon
    Project No.:

010 CH 356 H767401C / IM-010-F(204)A

    Location: 16 miles west of the Arizona/New Mexico State Line in Cochise County.
    Contractor: FNF Construction, Inc.
    Awarded: December 17, 2010
    Description: The project consists of milling and replacement of the existing Asphaltic Concrete in both lanes for eastbound and westbound I-10 from Milepost 367.67 to Milepost 385.03 and for eastbound I-10 from Milepost 356.5 to Milepost 357.7 in addition to the ramps at the East San Simon Traffic Interchange. The bridge rail will be replaced for the San Simon River Bridge (EB & WB), Cochise Avenue (EB & WB), and Luzena Road (EB) structures. Additional work consists of removal and replacement of guardrail, placing millings at specified crossovers, new striping and other related work.
    Duration: The time allowed for the completion of the work included in this project is 165 working days.
       

US 70 Gila River Bridge at Bylas

    Project No.: 070 GH 291 H691001C
      BR-STP 070-A(204)A
    Location:

Graham County on US 70 approximately 5 miles west of Bylas. Work begins at milepost 291.81 and extends easterly to milepost 293.74 for an approximate length of 1.9 miles.

    Contractor: FNF Construction, Inc.
    Awarded: November 18th, 2011
    Description:

The work includes removing the existing twenty three-span steel girder bridge and replacing it with a fifteen-span precast prestressed concrete AASHTO.

Type VI girder bridge. In addition, the project includes roadway approach widening, intersection improvement, guardrail reconstruction, berm construction, irrigation line installation, pavement markings placement and other miscellaneous work.

    Duration: The time allowed for the completion of the work included in this project will be 380 working days.
       

US 70 at Reay Lane Intersection

    Project No.: 070 GH 335 HX23101C
      STP-070-A(205)A
    Location: Graham County on US 70 at mile post 335.6 within the Town of Thatcher
    Contractor: C S Construction, Inc.
    Awarded: September 16, 2011
    Description: The proposed work consists of installing a new traffic signal, sidewalk ramps, and other related items at the intersection of US 70 and Reay Lane.
    Duration: The time allowed for the completion of the work included in this project will be 135 working days.
       
       

US 191 Bowie Junction – Safford Highway Segment V

    Project No.: 191 GH 100 H818501C
      STP-191-B(201)A
    Location: Graham County on US 191 at milepost 100.59 to milepost 104.52, approximately 15 miles south of Safford
    Contractor: CKC Construction & Materials LLC
    Awarded: December 17, 2010
    Description: The work includes the construction of two new northbound lanes east of the existing roadway with asphaltic concrete and asphaltic rubber friction course; construction of turnouts and reconfiguring the “T” intersection with SR 266; extend five reinforced concrete box culverts; extend 13 existing pipe culverts; construct 14 new pipe culverts; construct 23 new lateral storm drains and catch basins; overlay the existing pavement with asphaltic concrete and asphaltic rubber friction course; erosion control; seeding; signing; pavement marking; and other related work.
    Duration: The Department-Determined Construction Phase Time for substantial completion of the work shall be 500 calendar days.
       

US 191 MP 151.65 to MP 152.06 Slope Flattening

    Project No.: 191 GE 151 H790201C
      191-C-(206)A
    Location: Greenlee County about 9 miles south of Clifton on US 191 from mile post 151.65 to milepost 152.06
    Contractor: Show Low Construction, Inc.
    Awarded: September 16, 2011
    Description: The work under this project includes benching into the existing slope, adding fill material, mini benching for erosion control, slope rounding, and slope flattening. Also included in the work are pipe culvert extensions and remediation of existing pipe culverts, Class II seeding, erosion control elements of disturbed areas, and other related items.
    Duration: The time allowed for the completion of the work included in this project will be 120 working days.
       

US 191 Old Safford Road – Hill Street

    Project No.:

191 GE 159 H766501C

     

STP-191-C(209)A

    Location: The project is located in Greenlee County on US 191, beginning at MP 159.70 and ending at MP 163.69
    Contractor:  
    Awarded: Bid Opening May 13, 2011
    Description: The work consists of milling and replacing with asphaltic concrete pavement and asphaltic concrete friction course, pavement markings, replacement of guardrail end terminals, shoulder build-up, seeding, installing loop detectors and other related work.
    Duration: Time allowed for the completion of the work included in this project will be 100 working days.
       

US 191 Ward Canyon Bridge Repair

    Project No.: 191 GE 162 H671301C
      STP-191-C(208)A
    Location: US 191 milepost 162.65 in Greenlee County
    Contractor: C S Construction, Inc.
    Awarded: July 16, 2010
    Description: The work includes construction of a new retaining wall, drainage channel floors, concrete key and slope paving to protect the slope at one of the abutments of the Ward Canyon Bridge and other associated work.
   

US 191 San Francisco Bridge Replacement

    Project No.: 191 GE 163 H670801C
      BR-191-C(205)A
    Location: US 191 milepost 163 in Greenlee County
    Description: The project consists of removing the existing 366 foot long steel girder bridge, and replacing it with a 317 foot long, eight span closed frame continuous slab bridge. The work also includes removal and construction of concrete curb and gutter, sidewalk and driveways, construction of two approach slabs, riprap, placement of AC on the approach slabs and other related work.
    Duration: The time allowed for the completion of the work included in these two projects (Ward Canyon Bridge Repair and San Francisco Bridge Replacement) will be 200 working days.
       
 


Benson Construction ORG 8431

City of Bisbee Arizona Street, Hazzard Street - Cole Avenue

    Project No.:

0000 CH BIS SL64201C BIS-0-(200)A

     

0000 CH BIS SS77501C BIS-0-(201)A

    Location: Located in Cochise County in the City of Bisbee on Arizona Street beginning at Hazzard Street and extending 0.66 miles northeasterly to Cole Avenue.
    Contractor: K E & G Construction, Inc.
    Awarded: December 17, 2010
    Description: The proposed road work includes placement of aggregate base, asphaltic concrete, curb and gutter, a storm drain system, waterline replacement, signing, pavement markings, and other related work. The proposed enhancement work includes planting, irrigation, decorative walls and paving, bike bollards and street fixtures, pedestrian lighting, and other related work.
    Duration: The time allowed for the completion of the work included in this project will be 145 working days.
       

City of Sierra Vista Avenida Cochise at Oakmont Drive

    Project No.: 0000 CH SVS SH45401C
      HSIP-SVS-0(209)A
    Location: City of Sierra Vista located in Cochise County
    Contractor: K E & G Construction, Inc.
    Awarded: October 21, 2011
    Description: The work consists of the installation of an eastbound right turn lane and a traffic signal at the intersection of Avenida Cochise at Oakmont Drive. The work also includes video detection, pre-emption sensors, and modifications to the existing signing, pavement markings, and medians.
    Duration: The time allowed for the completion of the work included in this project will be 90 working days.
       

City of Sierra Vista Fry Blvd. – Buffalo Soilder Trail SR 90/92

    Project No.:

0000 CH SVS SS88801C

     

SVS-0(208)A

    Location: The project is located in Cochise County within the City of Sierra Vista on Fry Boulevard, from Buffalo Soldier Trail to SR 90/92, for an approximate distance of 2.88 miles
    Contractor: Southern Arizona Paving & Construction, Co.
    Awarded: March 18, 2011
    Description: Work included in the overlay project consists of: partial milling, furnishing and placing rubberized asphalt, pavement marking, resetting of the frame and cover of survey monuments, water valves, sewer manholes, and other related work.
    Duration: The contract time allowed for the completion of the work in this project is 70 working days.
       

I-10 Mescal Road Traffic Interchange (TI)

    Project No.: 010 CH 297 H833601C / ER-010-E(211)A
    Location: I-10 at Milepost 297.17 in Cochise County
    Contractor: Vastco, Inc.
    Description: The bridge rehabilitation project includes replacement of four columns at one pier, replacement of four pier caps, retrofit of abutments, installation of new precast, prestressed box beam girders, construction of the concrete deck, placement of approach slabs, painting of the existing and new portion of the bridge, pavement marking and other related work.
    Duration: The time allowed for the completion of the work included in this project will be 130 calendar days.
       

I-10 & SR 90 Traffic Interchange (TI)

    Project No.: 010 CH 300H650401C
      NH-STP-HSIP-TEA-010-E(200)N
    Location: Cochise County on I-10 at the State Route 90 Traffic Interchange near the City of Benson
    Contractor: Borderland Construction Co., Inc.
    Awarded: September 1, 2010
    Description:

   Project Web site
The project will reconstruct the I-10/SR 90 TI overpass structures, SR 90 below the overpass, entrance and exit ramps in both directions, realign and reconstruct I-10 mainline west of the TI, construct three access roads (W. Dark Star Road, N. Vidal Trail and W. Calvary Lane), drainage improvements, lighting, utility relocations, signing and marking, and other related work.
    Duration: The time allowed for the completion of the project is 500 working days.
       

SR 80 Tombstone - Jct SR 90

    Project No.: 080 CH 318 H574101C
      STP-080-A(206)A
    Location: Cochise County on State Route 80 between the Town of Tombstone and the junction with State Route 90
    Contractor: Bison Contracting Co., Inc.
    Awarded: October 15, 2010
    Description:

The work consists of extending box culverts and pipe culverts, removing and replacing pipe culverts and signing, removing embankment curb and spill ways, and performing other related work.

    Duration: The time allowed for the completion of the work included in this project will be 235 working days.
       
 