1. What does the outcome of the Gila River Indian Community’s vote mean for the South Mountain Freeway study? Will an alignment on the Gila River Indian Community be considered?
The Gila River Indian Community’s (GRIC or Community) vote on February 7, 2012 represents an important milestone for the South Mountain Freeway Study.
At the request of the Gila River Indian Community in January 2010, the Arizona Department of Transportation (ADOT) and MAG worked together to identify a potential freeway alignment on Community land. The alignment followed a route consistent with the Community’s 1998 Gila Borderlands Regional Planning Study. When no “fatal flaws” were identified, in late 2011 the Community Council passed a resolution to hold a Community-wide referendum on the freeway. The referendum asked members whether they supported an on-Community alignment, supported an off-Community alignment, or whether they supported a “no-build” alternative.
The GRIC election on February 7, 2012 preferred the “no-build” option for construction of the Loop 202 South Mountain Freeway. This means, moving forward, an alignment of the South Mountain Freeway cannot be located on the Gila River Indian Community. The Pecos Road Alternative will be carried forward in the Draft Environmental Impact Statement (EIS), as well as the consideration of a No-Build Alternative. The Community’s position regarding “no-build” will be considered as part of the Draft EIS.
As the process moves forward, ADOT and MAG will continue to coordinate with the Community on remaining concerns and potential methods for mitigating those concerns.
2. Has MAG made any recommendation regarding the 59th Ave alignment?
In October 2009, the Maricopa Association of Government’s (MAG) Regional Council voted to approve the revised Regional Transportation Plan (RTP). This plan includes the shift of the Western Section alignment between Lower Buckeye Road and Interstate 10 (I-10) to connect at 59th Avenue (rather than 55th Avenue).
3. Why has the 55th Avenue Alternative been moved to 59th Avenue?
Responding to budget shortfalls created by declining revenue, MAG began to study methods to reduce freeway costs. There was also public concern about the number of potential residential and business acquisitions. From this analysis – two key changes were made:
- Reduce the proposed freeway to eight lanes from ten, which allows the needed right-of-way to be reduced;
- Shift the alignment to connect with the I-10 at 59th Avenue.
4. What is the status of the EIS?
ADOT is currently revising the Administrative Draft Environmental Impact Statement (Draft EIS) and preparing the document for legal and cooperating agency review. Following these review processes, the Draft EIS will be prepared for public release.
5. What is the status of the "parkway" proposal? Is it even being given due consideration???
The study team and ADOT provided MAG with a number of concepts, cost estimates, and an impact analysis for a parkway concept, either as the final configuration or as an initial phase of building a freeway. The MAG Transportation Policy Committee ultimately decided not to include a parkway concept as the recommended type of roadway for the proposed project due to the projected traffic demand and operational concerns.
6. Has a corridor along Pecos Road already been decided?
No, however the Pecos Road route was identified as a result of the 1988 state-level Environmental Assessment (EA). This alternative, along with the consequences of not building the freeway, are currently being studied. Currently, the Pecos Road alignment is the only eastern section alternative under consideration in the Draft EIS.
7. Why is ADOT conducting a second environmental study?
Much has changed in this area since the 1988 state-level EA was completed. The Draft EIS is being prepared in light of new development in the area as well as changes in design standards and environment regulations, and to qualify for federal funds.
8. If the Pecos Road alignment is not a foregone conclusion, then why has ADOT purchased right-of-way along that alignment?
ADOT purchased some right-of-way in the corridor along Pecos Road when it was adopted as the alignment in 1988. Currently, ADOT is acquiring right-of-way to preserve the viability of the corridor and to minimize future relocation of homes and businesses as part of the agency’s long-range planning efforts. Should another alternative be adopted as a result of this study, ADOT can dispose of the land that has been acquired but is no longer needed.
9. Will the fact that ADOT already owns right-of-way in this corridor influence the final decision?
No, FHWA regulations do not allow the ownership of right-of-way to be a factor in the decision regarding the adoption of an alternative.
10. What factors will be considered in choosing an alternative?
A major factor is how well an alternative might improve future mobility, while minimizing impacts on the built and natural environment. Some factors that will be considered include air quality, cultural sites, environmental justice, threatened and endangered species, potentially hazardous materials, residential and business relocations, utilities, local land use plans, agricultural lands, traffic operations, cost, noise, historic/public park land and public and jurisdictional acceptability.
11. What about truck traffic that might be generated by a new highway?
One of the factors that will be considered in this study is the amount of truck traffic that would be generated and its potential impact on the surrounding community. The MAG regional travel demand model forecasts approximately 10 percent truck traffic on the South Mountain Freeway in 2035. The forecast truck traffic is based on existing traffic studies and projected socioeconomic data. This percentage is similar to the current conditions on I-10 between Loop 101 and I-17 and on US 60.
12. Will the public have a voice in choosing an alternative?
Yes, an extensive effort is ongoing to keep the public informed of the progress of the study and to gain public input. Issues, concerns and opportunities expressed by citizens will be considered in the ultimate decision of whether or not to build the proposed freeway, what should be built and where it should be located.
13. Will anything other than a freeway be considered?
Other non-freeway alternatives have been considered. Among other things, the study takes into account improving existing freeways, improving or expanding other travel modes, strategies to reduce travel demand, and various roadway configurations. This study will examine not only the potential impacts from improvements, but also the consequences of building nothing. As proposed by the Maricopa Association of Governments, the South Mountain Freeway would be part of the regional freeway system – a multimodal approach to improve traffic in the Valley as part of the Regional Transportation Plan. Other transportation improvements, like mass transit and local roads are specified in the Regional Transportation Plan and are considered during the evaluation of this proposed new freeway.
14. Is it possible that nothing will be built?
Yes, that is one of the options being studied. It is important to recognize that impacts can occur by doing nothing. The no-build alternative is being evaluated in the Draft EIS.
15 Would air, noise and visual quality be impacted by construction of a new road or freeway?
A major purpose of this study is to determine the potential impacts on air, noise and visual quality and to look for ways to lessen those impacts. The South Mountain Freeway is a large complex project and the study team is analyzing potential impacts.
16. How long will this study take to complete?
The study began in July 2001. Traditionally, this type of study takes five to seven years to complete. However, this will ultimately be determined by issues and impacts that are discovered during the course of the study. Based on current progress, ADOT anticipates that a final decision will be reached by the end of 2013.
17. When is something likely to be built?
If the outcome of this study is a build alternative, the timing of construction will depend upon funding availability in conjunction with final design completion, right of way acquisition, and utility relocation. As part of the current study, a document called an Implementation Plan will be produced. This document will recommend how to construct the overall project, including the length of construction segments and a sequence for those segments. The Implementation Plan might also recommend improvements to existing roadways within the study area. A South Mountain Freeway build alternative is included in the RTP; exact timelines for funding are determined annually through the Five-Year Program planning process. The current Five-Year Program includes funding for construction of the freeway in fiscal year 2014.
18. Where would the corridor join I-10 to the west of Phoenix?
ADOT has designated the 59th Avenue connection (W59) with I-10 (Papago) as the preliminary preferred alternative for the West Valley connection. This is an adjustment from an earlier decision identifying 55th Avenue (W55) as the western connection.
19. Is it likely that construction of a new road or freeway would require the acquisition of existing homes or businesses?
It is likely that the proposed South Mountain Freeway would require the acquisition of a number of existing homes and/or businesses. One purpose of this study is to determine the extent of new right-of-way that would be needed for each possible alternative. ADOT continues to work with all Valley municipalities to protect possible freeway alignments as part of a commitment to measured growth. With changes to the Regional Transportation Plan, ADOT already owns more than 90 percent of the needed right-of-way along Pecos Road, should that alternative be approved for construction.
20. Isn’t the real purpose of a South Mountain Freeway simply to act as a bypass to divert trucks from downtown Phoenix?
The primary purpose of this study is not to create a "truck bypass" for downtown Phoenix. The study is intended to assess the overall transportation needs of the entire Phoenix metropolitan area and to determine the best way to meet those needs. This proposed freeway is part of a regional system, which was developed to improve mobility in the region by increasing capacity and providing alternatives to allow traffic, including truck traffic, to bypass already congested routes. Like other “loop” freeways in Metro Phoenix, the proposed South Mountain Freeway would be a commuter corridor, helping to move local traffic between the east and west portions of the Valley. In fact, a truck bypass route already exists using I-8 and State Route (SR) 85. This route is clearly marked for trucks and is a designated routing for CANAMEX traffic. Many of the trucks you see in the metro area need to come into the city core – either to make deliveries, to access terminals, or for other commercial activities.
21. How is an Environmental Impact Statement different from the Environmental Assessment that was conducted in 1988?
The 1988 state level Environmental Assessment was prepared in order to satisfy state requirements only. In order to make any resulting project eligible for federal funding, the current study will satisfy federal requirements and will have to comply with the National Environmental Policy Act. Under this act, an Environmental Impact Statement is required for this project due to the potential of substantial impacts on the environment and surrounding communities. An Environmental Impact Statement is different from an Environmental Assessment in that it will address in detail a number of alternatives to satisfy the transportation needs in the corridor. The Draft Environmental Impact Statement is currently under review by the various government agencies involved with the project.
22. Will the current study be influenced by the 1988 Environmental Assessment?
The current study, known as an Environmental Impact Statement, will not supplement or update the 1988 state level Environmental Assessment. It is an entirely separate study and will not depend on the data collected in 1988. The 1988 Environmental Assessment was prepared in order to satisfy state requirements only. In order to make any resulting project eligible for federal funding, the current study will satisfy federal requirements and will comply with the National Environmental Policy Act.
23. The future is light rail so why would ADOT even consider building another freeway, which will only add to our congestion and air pollution problems?
The study will consider feasible alternatives, including light rail transit, travel reduction strategies, improving existing roads, and the consequences of doing nothing at all. ADOT and the Maricopa Association of Governments seek multimodal options for supporting the needs of the traveling public in the Valley. Transportation options are designated through collaborative, long-range planning processes by MAG as the regional planning authority.
24. If ADOT builds a freeway, will it be built wide enough so it doesn’t have to be torn up and rebuilt in a few years?
The South Mountain Freeway would be constructed as an eight-lane freeway (three general purpose lanes and one HOV lane in each direction). The freeway would not be designed to accommodate future widening. This change in scope will still meet the transportation needs of the Valley, but reduce costs at a time when revenues have dropped significantly.
25. Will the Environmental Impact Statement include an analysis of the amount of diesel fumes that someone living adjacent to a freeway might be exposed to?
Potential changes in air quality are one of the key areas that will be studied in the Draft Environmental Impact Statement.
26. Once an alignment is decided, will we have a year or so to make our case?
This study, which began in July 2001, is expected to be completed by 2012. During the study process, community members will have various formal and informal opportunities to ask questions, express opinions and provide comments about the proposal. We will work to involve the public in this investigation and decision-making process throughout the study. The environmental report will have a 90-day comment period, public hearings and additional comment time for the Final EIS to incorporate layers of public input.
27. What can we do to get Pecos Road taken off the board?
The Pecos Road alignment for a South Mountain Freeway was identified in a state-level Environmental Assessment completed in 1988 and that alignment was adopted by the State Transportation Board. However, as part of the current study all reasonable alternatives are being considered. The Pecos Road alignment is considered a reasonable alternative in conjunction with a western section alternative which would meet the established purpose and need. At this time, there are no other reasonable and prudent alternatives in the eastern section.
28. If it won’t help traffic congestion (in Ahwatukee) why consider building a freeway?
When ADOT determines if a freeway should be built, the agency must consider numerous factors including local and regional transportation needs, project costs and environmental considerations. This decision has to be based on the transportation needs of the entire Phoenix metropolitan area as part of a comprehensive, regional approach to transportation solutions. Furthermore, this freeway was proposed as part of a regional plan that ADOT is charged with studying, but which is developed collaboratively by citizens and leaders from across the Valley through MAG.
29. Are other viable alternatives in Ahwatukee, other than the Pecos Road alignment, being considered?
Other alternatives were considered during the alternatives analysis phase of the study, but were eliminated from consideration due to their substantial impacts or their inability to satisfy the purpose and need of the proposed action; these alternatives were located north of Pecos Road. The only alternatives in the Ahwatukee portion of the study area that are still being considered are the Pecos Road alignment or not building the freeway.
30. Will the study include potential increases in crime that might result from having a freeway built through our community?
The Environmental Impact Statement will not include an official assessment of crime statistics. However, the City of Phoenix has provided information to the Citizens Advisory Team addressing this issue. While Phoenix Police indicated there was not specific data on a correlation between freeways and crime rates, the incidences of criminal activity seemed to be related more to the type of development adjacent to a freeway.
31. Would the potential freeway be built below existing ground?
The study team is currently in the process of analyzing the below-ground option with a smaller freeway configuration (eight lanes). The results of this analysis will be part of the Draft EIS and Location/Design Concept Report. However, it is anticipated that the change to a smaller configuration would not change the overall conclusions from the original analysis. Results of the original analysis indicated that in an effort to reduce impacts by depressing the freeway in the eastern section, ADOT would be required to spend an additional $400 million for construction and right-of-way, displace an additional 300 residences, maintain additional pump stations and detention basins for the life of the freeway, and would still have noise-related impacts requiring mitigation. Due to the fact that the below-ground option would result in substantially greater costs and residential displacements, this option was previously eliminated from further study. Freeways in the region all have above- and below-ground segments, as is proposed with this corridor.
32. Where would the interchanges be located?
Potential traffic interchange locations are being considered at approximately one-mile intervals at major street crossings. ADOT has been working with local communities and jurisdictions regarding potential locations. The following locations are currently proposed:
Western Section
Van Buren Street
Buckeye Road
Lower Buckeye Road
Broadway Road
Southern Avenue
Baseline Road
Dobbins Road
Elliot Road
Eastern Section
51st Avenue
17th Avenue
Desert Foothills Parkway
24th Street
40th Street
The locations are not final. ADOT is still in the process of coordinating with the affected jurisdictions.
33. How much influence will developers have in this process?
No more than any other citizen.
34. Will the City of Phoenix be able to influence the study?
The City of Phoenix represents the citizenry of a major portion of the study and is an active participant, as are the other municipalities and regional planning organizations in this area. As a member agency of the Maricopa Association of Governments, the City will have an opportunity to grant funding/approval should the project advance.
35. Would the high water table near the Salt River preclude construction of a depressed freeway?
The data that we are currently collecting about the study corridor will include such things as water resources and groundwater levels. This information will help us determine the types of design alternatives that would be feasible. This information will be available both in the Water Resources Technical Report as well as the EIS.
36. Would this freeway be part of the planned CANAMEX highway?
No. It is not the intent of ADOT or FHWA to include this proposed freeway as part of the CANAMEX corridor. In fact, the CANAMEX corridor in Maricopa County takes trucks from I-10 south of the Valley across I-8 to State Route 85, avoiding the metro-Phoenix area. Improvements are under way to convert this route into a higher-capacity, freeway quality route.
37. How would the existing Santan/Interstate 10 Interchange connect to the west?
The existing interchange was designed as a temporary connection with Pecos Road. It also is designed so that a permanent connection with the proposed South Mountain Freeway could be made if the freeway would be constructed on or near the Pecos Road alignment.
38. Will anything be built through South Mountain Park/Preserve?
Federal restrictions prohibit intrusion of a federal project such as this into a park, like South Mountain Park/Preserve, unless it can be shown that there is no feasible and prudent alternative to avoid such an intrusion. At this time, the study team has not identified feasible and prudent alternatives to avoid impacts on the park. As such, the freeway would go through the southern limits of the park. ADOT is working closely with park stakeholders to minimize impacts and address various concerns.
39. Can the Pecos Road corridor be changed?
Yes, the Pecos Road corridor was identified as the most appropriate alternative in 1988. However, the Environmental Impact Statement will consider a range of reasonable, present-day alternatives. However, at this time, no other alternatives have been identified. Should those options be presented for study, the team will fully evaluate.
40. What are the other alternatives?
Through the study’s public involvement efforts, over 30 alternative freeway routes were initially proposed. The study team evaluated the intent of each of these routes and developed a series of alternatives that were evaluated during an initial alternatives screening effort.
The screening of these alternatives resulted in three connection alternatives (55th Avenue, 71st Avenue and Loop 101) on the west side of the study area and one (Pecos Road/Loop 202) on the east side of the study area. In response to budget shortfalls created by declining revenue, MAG began to study methods to reduce costs. This analysis resulted in a shift of the 55th Avenue alternative to 59th Avenue. These alternatives, with variations, are being analyzed in detail in the Draft Environmental Impact Statement.
41. Will storm water runoff be controlled? Where will the water go?
If a new freeway is built, it would be designed to control storm water runoff and prevent flooding. In the western section, runoff would be discharged into the Salt River. In the Eastern Section, runoff would be discharged to the south to the Gila River Indian Community. The rate of discharge would not be greater than the existing rate of discharge.
42. Will there be access to the Gila River Indian Community from the traffic interchanges in the Eastern Section?
Federal law prohibits the denial of access to any community. The traffic interchanges would give the Gila River Indian Community access to the freeway if a roadway is constructed from the south.
43. If we can look forward to a level of service "F" in the future, what level of service do we have now?
Current level of service varies according to the time of day. We already are experiencing level of service "F" on some freeways during morning and evening rush hours. Traffic projections show, however, that this condition is likely to occur more often and last for longer periods of time in the future without improvements to the Regional Freeway System.
44. What is pass-through traffic?
Traffic that neither starts nor ends in the Valley is referred to as “pass-through.” An example is I-10 traffic that originates in Los Angeles and passes through the Phoenix area without stopping on the way to El Paso.
45. Has anyone looked at Riggs Road as a truck bypass?
During initiation of the Environmental Impact Statement process, according to protocol, ADOT approached the GRIC Natural Resources Standing Committee (NRSC) with a request to study alternatives on Community land as far south as Riggs Road, an often-suggested possible route by the public.
Nearly two-thirds of the alternative would be on Community land. While the Riggs Road Alternative would serve regional mobility needs, particularly of those living in the Maricopa area, meeting this travel demand would not address any specifically identified planning goals for an integrated regional transportation network. The Regional Transportation Plan identifies the proposed freeway as a critical link in the Regional Freeway System, both in completing it and in optimizing overall system performance as well as that of specific existing links such as Loop 202 (Santan Freeway). The Riggs Road Alternative would not complete the Loop 202 system, thereby causing substantial out-of-direction travel for motorists. The alternative would not be prudent and feasible because it would not meet the proposed action’s purpose and need and, therefore, was eliminated from further consideration.
46. Why not do what was done with the Loop 101 in Scottsdale: pay the Indian Community for the land and put it there?
ADOT continues to discuss a range of transportation-related topics with the Community. Ultimately, it is up to the Community, as a sovereign nation, to decide whether it will allow an alignment on its land. Discussions are ongoing between ADOT, MAG, FHWA and GRIC to allow the exploration of additional alternative options.
47. What kind of freeway design would be needed for the Pecos Road alignment?
Traffic studies show that a freeway, similar to the Pima Freeway or Red Mountain Freeway would be needed on the Pecos Road alignment. Potential impacts will be presented officially in the Draft EIS.
48. Have you determined how many vehicles would be likely to use the highway?
It is estimated that up to 170,000 vehicles per day will be using the South Mountain Freeway each day in 2035.
49. Will trucks carrying hazardous cargo be allowed to use the highway?
Yes, the only freeway locations in the Valley where hazardous cargo is prohibited is I-10 through the Deck Park Tunnel and on Loop 202 (Red Mountain Freeway) along the mile-long bridge above the Salt River in Tempe. Such restrictions on this freeway are not anticipated at this time.
50. What impact would a freeway along Pecos Road have on the area’s air quality?
An air quality analysis will be conducted for each of the alternative alignments. The results of the analysis will be included in the Draft Environmental Impact Statement.
51. How do you know what the air quality impact will be before the freeway is built?
Air quality impacts are determined through sophisticated computer modeling based on predictions of the amount and nature of traffic under the worst case scenarios. The Maricopa Association of Governments provides regional air quality analysis. ADOT also conducted detailed analysis of weather patterns, at the request of community members.
52. Has a decision been made on the purpose and need for a freeway?
Yes, based on projections of population growth in the Valley, increases in the number of vehicle miles traveled, and where residences and businesses will be built, it has been determined that there is a need for an I-10 to I-10 connection of some nature south of South Mountain. We are in the process of analyzing alternatives make this connection.
53. Would the proposed South Mountain Freeway handle all of the excess traffic that is anticipated in 2030?
No, there is no single freeway that can accomplish that. This proposed roadway is seen as a part of the overall system improvements and expansion that will be needed to handle our future traffic. To address future needs, the Regional Transportation Plan includes several new and expanded freeways, improvements to I-10 in the Broadway Curve and enhancements to US 60, busing expansion, and additional studies into light rail transit. All of these projects are designed to work together to better meet the Valley’s transportation needs.
54. We don’t trust your traffic projections. We think they are flawed. Who will ensure that the projections are accurate? Who will gather the data?
The traffic projections are developed by the Maricopa Association of Governments using travel demand software that is certified by Federal Highway Administration and reviewed by the Environmental Protection Agency for air quality conformity. Final acceptance of the projections will be given by ADOT and the Federal Highway Administration.
55. How has passage of the proposed extension of Maricopa County's ½ cent transportation sales tax (Proposition 400) in the November 2004 election affected the future of the proposed South Mountain Freeway?
Passage of Proposition 400 provides the primary source of funding for construction of the South Mountain Freeway.
56. Why did ADOT select the 55th Avenue alignment as the preferred western alignment and not the proposed 71st Avenue or Loop 101 alignments?
The 55th Avenue (now 59th Avenue) Alternative was identified as the Preliminary Preferred Build Alternative after comparing each of the proposed South Mountain Freeway alternatives in terms of addressing regional transportation needs, consistency with regional and long-range planning, environmental and societal impacts, traffic operational efficiencies, estimated costs and regional and public support. The Citizen’s Advisory Team recommended the W101 connection. However, the study team considered the input of all stakeholders – including regional leaders, municipalities, historical planning, and public/CAT input – to preliminarily identify the 59th Avenue alignment as the preliminary preferred western alignment to assist with needed incremental planning as the freeway study progressed. The final alignment selections will be identified in the EIS and Record of Decision.
57. Would the eastern or the western section be constructed first?
Assuming the outcome of this study is a build alternative, the construction schedule would be determined as part of the Implementation Plan. This document would be created during final design and would recommend how to construct the overall project, including the length of construction segments and a sequence for those segments. It is anticipated that the freeway construction would begin in the Western Section. Ultimately, both sections need to be built, as required under federal regulations for new highways to have independent utility and a logical termini.
58. Is this freeway going to have elevated interchanges?
It is anticipated that most of the interchanges would be elevated. However, the design of each of the interchanges has not been decided.
59. Who makes the final decision? Who has the power to make a decision?
The final decision on the freeway alignment is a cooperative effort, involving ADOT, the Federal Highway Administration, and the Maricopa Association of Governments. As a corridor that is part of a comprehensive regional plan developed by MAG, ADOT serves as the agency responsible for implementation of the plan with FHWA providing federal oversight required to access federal funds.
60. Is there a guarantee ADOT will buy the homes and businesses that lie within proposed right-of-way lines on the maps?
The right-of-way lines are based on the best information available today. The lines are identified to show the area of impacts, and are a good estimate of the area necessary to construct a freeway. Some refinement of these lines would take place during the design phase, which would identify the exact properties that would need to be acquired. With specific questions about proposed right-of-way impacts, contact the ADOT Right-of-Way Group at 602.712.7316.
61. What if I own property in an alignment?
New right-of-way maps are available. Determination of the final right-of-way would be made during the design phase and involve coordination with local and regional governments should a build alternative be selected. If you have any concerns about a specific property related to the proposed South Mountain Freeway, you can contact the ADOT Right-of-Way Group at 602.712.7316.
62. Are there more meetings the public can attend before a decision is made?
At a minimum, there will be public hearings held after the Draft Environmental Impact Statement is made available to the public during the 90-day public comment/review period. A timeframe for those hearings has not yet been established. A public information meeting was held from 6-8 p.m. on Feb. 10, 2010 at Sunridge Elementary School to provide information about the W59 Alternative.
63. How is public input used?
Public comments are a vital component in the decision-making process. The interests and needs of the public along with all other social, economic, and environmental issues and impacts must be fully analyzed and included in the Final Environmental Impact Statement. Comments made during the Draft EIS development have and will continue to be used to adjust plans, explore new questions or make changes within the scope of NEPA. Additional comment periods will be available when the Draft EIS is available for public review, and when the Final EIS is released for public review.