I-17: Junction SR 179 to I-40

   

The Arizona Department of Transportation and the Federal Highway Administration as lead federal agency are conducting engineering and environmental studies to develop a long-range plan for the improvement of the Interstate 17 corridor between the State Route 179 traffic interchange (Sedona turnoff) and the Interstate 40 traffic interchange in Flagstaff. A series of improvements will be developed to provide for greater capacity and to ensure smooth operations for the traffic volumes that are projected to occur over the next 20 to 30 years. The design concept report will consider roadway, bridge, and drainage improvements. Environmental issues will also be assessed. When the reports are complete, potential projects will be identified and priorities established for future inclusion in ADOT’s construction program when funding is available.

Study Timeline

Winter 2007 - Fall 2008
  Develop & evaluate alternatives, prepare environmental overview

Spring 2009

  Public information meeting to present alternative selection report
Summer 2009 - Spring 2011
  Prepare engineering and environmental documents
Fall 2011
  Public hearing to present recommended alternative
Winter 2011
  Finalize documents; agency acceptance

Publications

Project Information Contact:
MacKenzie Kirby
Flagstaff District Senior Community Relations Officer
928.779.7554

 

To Submit Comments:
Amy Rosar
Public Involvement Specialist
KDA Creative
602.368.9644

 

    Arizona Department of Transportation    
   Disclaimer & Privacy Statement  |   Contact ADOT